# Server Farms Are Not Yet Complete — but Have Already Boosted Mega Or's Profit

*Mega Or posted a 34% jump in net profit in the third quarter • Most of the growth was driven by accounting revaluations of computing facilities that have not yet begun operating • The company faces a funding gap of nearly NIS 11 billion and a bottleneck in the power grid*

- Published: 2026-11-11T11:26:47.815Z (Wednesday, November 11, 2026)
- Updated: 2026-11-12T20:22:56.967Z
- By: Sharon Birkman
- Section: TASE Stocks
- Canonical: https://tv10.news/news/capital-market/tase-stocks/127068/unfinished-server-farms-boost-mega-or-profit/
- Hebrew original (TV10): https://tv10.co.il/news/capital-market/tel-aviv-stocks/127068/
- Publisher: TV10 Global (TV10, Israel’s economic channel). Translated from Hebrew with AI and an automated accuracy check.

Income-producing real estate company Mega Or, [which recently joined the TA-35 index](https://tv10.co.il/articles/דרמה-בבורסה-בתא-עדכון-המדדים-מחר-צפוי), reported quarterly net profit of NIS 243.1 million and NIS 1.18 billion in the first nine months of 2026. Net profit rose to NIS 243.1 million, while revaluation gains of NIS 276.2 million were recorded at the operating level. The increase in value was about NIS 212 million higher than in the corresponding quarter, while net profit, which also takes taxes and other items into account, grew by about NIS 62 million. The increase in value is already being recorded in the financial statements.

![Server farm, illustration](https://tv10.news/media/2026/11/32/3263a2bbd1f62a695f4b0ed4561ca2ae3110d443c077f6a93a426ca5605d3f08.jpg)

Server farm, illustration | Photo: Shutterstock

Mega Or [currently operates one server farm in Modi'in](https://tv10.co.il/articles/במיליארד-שקל-מגה-אור-רכשה-את-הקרקע-של-מ), but a presentation published for its investors shows that it has a pipeline of eight facilities and expansion phases in Israel with a total capacity of 486 megawatts of IT. The company expects its representative annual NOI to jump more than 4.5-fold by the end of 2029 — from NIS 506 million today to NIS 2.335 billion, with server farms contributing about NIS 1.74 billion, nearly 75% of the total. The company is expected to deliver three of them to customers by the beginning of 2027: the expansion in Modi'in, the facility in Yoav and the first phase in Beit Shemesh. The full capacity in Modi'in and Beit Shemesh has already been ordered, while 75% has been ordered in Yoav and the remainder has been reserved for a customer under a signed agreement. The two largest phases, another expansion in Beit Shemesh and a facility in Hadera, which account for almost half of the capacity under construction, are expected to be delivered in 2029, but the company has not yet presented orders for them. The company also disclosed that the processing of electricity connection requests for its future land reserves has been frozen under a temporary government order. At the same time, the company's board approved an examination of expansion into this field in Europe as well.

Revenue from rent and property management rose by about 23% to NIS 101.5 million, while net operating income from the properties, or NOI, grew by about 18% to NIS 122.4 million. The increase in same properties totaled 3%. FFO under management's approach, a measure of ongoing profitability in the income-producing real estate sector, rose by 17.5% to NIS 91.5 million.

![Stock investment, illustration](https://tv10.news/media/2026/11/54/5417e5aea8f5e989c2082a3ac688e9038096eff55c5bc04bc568482ca8bdb4d0.jpg)

Stock investment, illustration | Photo: Shutterstock

At the end of September, Mega Or's net financial debt stood at 43% of its total balance sheet. By the end of 2028, [the company is expected to repay principal on bonds and loans totaling nearly NIS 3 billion](https://tv10.co.il/articles/צחי-נחמיאס-ומגה-אור-בגיוס-מוצלח-המוסדי), alongside investments in the construction of server farms, logistics and commercial centers, and energy facilities. Mega Or estimates that completing all projects under construction will cost an additional NIS 10.75 billion, an amount that also includes projects scheduled for delivery in 2029. At the end of September, the company had NIS 527 million in cash and marketable securities, NIS 350 million in unused credit facilities and unencumbered assets valued at about NIS 9.2 billion.

Mega Or shares have risen 73% since the beginning of the year and are currently up about 4%.
