# Sorek Power Plant Gets Underway: Financial Close Completed for NIS 5 Billion Project

*The power plant, with a planned capacity of about 850 megawatts, is expected to begin operating in 2029 and supply electricity to the Tel Aviv metropolitan area and the national grid • Edeltech Group and Menora will finance, build and operate it for about 25 years*

- Published: 2026-11-04T18:38:51.968Z (Wednesday, November 4, 2026)
- Updated: 2026-11-12T20:11:18.142Z
- By: TV10 Desk
- Section: Energy
- Canonical: https://tv10.news/news/energy-infrastructure/energy/126752/sorek-power-plant-financial-close-nis-5-billion-project/
- Hebrew original (TV10): https://tv10.co.il/news/environment/energy/126752/
- Publisher: TV10 Global (TV10, Israel’s economic channel). Translated from Hebrew with AI and an automated accuracy check.

**The Sorek power plant project is advancing to the construction stage:**The special tenders committee at the Ministry of Finance announced today (Wednesday) that financial close had been completed for the project, involving an investment of about NIS 5 billion. The plant, which will have a capacity of about 850 megawatts, is expected to begin operating in 2029 and strengthen the reliability of the electricity supply to the Tel Aviv metropolitan area and Israel’s electricity sector.

The project was awarded to Edeltech Group and Menora through a PPP (public-private partnership) tender. The group will be responsible for financing, planning, building, operating and maintaining the plant for about 25 years.

The power plant will be built at the Sorek complex, near the Sorek A and Sorek B desalination facilities and the Shafdan facility. It will use combined-cycle technology based on natural gas and will include an advanced Siemens H-class gas turbine. The technology enables higher energy efficiency and reduces fuel consumption and emissions compared with older generation technologies.

The construction period is expected to last about 36 months. The plant’s location, near the Tel Aviv metropolitan area and Israel’s major population and economic activity centers, is intended to address the expected growth in electricity demand in the coming years, partly due to population growth, expanding economic activity and the transition to increased electricity use.

The plant’s operation is expected to increase Israel’s private electricity generation capacity and strengthen competition in the electricity sector, while expanding the amount of available and reliable generation. The plant will participate in the electricity generation market under regulations set by the Electricity Authority.

The financing close is a significant milestone in the project, following a lengthy tender, engineering and regulatory process. It is being advanced by a special tenders committee chaired by Gal Landau, director of the Infrastructure and Projects Unit in the Accountant General’s Department at the Ministry of Finance, with the participation of representatives from the Ministry of Finance, the Ministry of Energy and Infrastructure, the Electricity Authority and Inbal.

Deputy Accountant General Oshrat David-Deker said the transition to the construction stage is a significant achievement that demonstrates the state’s ability to advance complex national infrastructure projects and the advantages of cooperation between the public and private sectors.

Ministry of Energy and Infrastructure Director General Yossi Dayan added that the plant will strengthen Israel’s energy security and its ability to provide electricity reliably and continuously, particularly in the central region, where major population and economic activity centers are concentrated.