BAZAN May Petition Court Over Maintenance Delay Causing $500,000 in Daily Damage
The Ministry of Environmental Protection has yet to approve the resumption of work at the aromatics facilities of subsidiary Gadiv in Haifa • BAZAN says it met all requirements and is considering legal action • Work on the key CCR facility is progressing as planned and may even be completed ahead of schedule