Timnat Energy and Colmobil to Build Solar-Storage Project in Hatzor

The project at the kibbutz’s reservoirs is expected to generate about NIS 10.5 million in revenue in its first year and supply electricity to about 2,000 households for 24 years • The facility will have 9.2 megawatts of installed solar capacity and 68.4 megawatt-hours of storage capacity

Renewable energy
Renewable energy | Photo: Shutterstock

Timnat Energy and Colmobil Energy reported that they had jointly won a tender to build a solar power generation project combined with energy storage at Kibbutz Hatzor’s reservoirs.

NIS 100 and NIS 200 banknotes
Cash | Photo: Shutterstock

The project, involving an investment of about NIS 70 million, is expected to generate revenue of about NIS 10.5 million in its first year of operation.

Dual Use of Existing Infrastructure and Electricity Generation Volumes

The project is based on the dual use of existing water infrastructure and will include solar systems installed on the sides of the reservoirs alongside floating solar systems on the water. The facility will have 9.2 megawatts (MWp) of installed solar capacity and 68.4 megawatt-hours (MWh) of storage capacity, with a high-voltage connection to the power grid rated at 13.68 megawatts (MWac).

Solar panels
Solar panels | Photo: Shutterstock

The system is expected to generate about 15.7 million kilowatt-hours a year, an amount equal to the annual electricity consumption of about 2,000 households. Over the planned 24-year operating period, the facility is expected to generate about 360 million kilowatt-hours of electricity and prevent about 8,000 tons of carbon dioxide emissions a year.

Timetable and Response to the Energy Market’s Needs

The companies are currently working to advance the project’s development stages, with construction scheduled to begin at the end of 2027 and commercial operation expected at the end of 2028.

Against the backdrop of the expected increase in electricity demand, integrating the storage system will make it possible to store electricity generated during the day and feed it into the grid in the evening and during peak demand hours, thereby contributing to the flexibility and reliability of the country’s electricity supply.

Energy sector
Energy sector | Photo: Shutterstock

The latest win follows the companies’ announcement last week that commercial operations had begun at the Lambrinovo project in Bulgaria, a battery electricity storage facility with a capacity of 150 megawatts and an investment of about 60 million euros.

Companies’ Response

Dan Naor, CEO of Timnat Energy, said winning the Hatzor project represents another milestone in establishing the company’s position in the renewable energy market, and welcomed the agreement with Kibbutz Hatzor and the cooperation with Colmobil Energy.

He said the project reflects the company’s ability to lead complex projects from the development stage through ongoing operations.

Timnat Energy CEO Dan Naor
Timnat Energy CEO Dan Naor | Photo: Inbal Marmari

Aviv Peper, CEO of Colmobil Energy, added that this is a long-term project combining economic potential with smart use of existing infrastructure.

Peper also said the partnership with Hatzor and Timnat demonstrates how to build relationships of trust and turn a shared vision into an asset that generates value over time and strengthens Israel’s energy market.

Key takeaways

  • Timnat Energy and Colmobil Energy jointly won a tender to build a solar power and storage project at Kibbutz Hatzor’s reservoirs.
  • The project requires an investment of about NIS 70 million and is expected to generate about NIS 10.5 million in its first year.
  • The facility will have 9.2 megawatts of installed solar capacity and 68.4 megawatt-hours of storage capacity, with a 13.68 megawatts grid connection.
  • It is expected to produce about 15.7 million kilowatt-hours a year, enough for about 2,000 households, and operate for 24 years.
  • The companies said construction is scheduled to begin at the end of 2027, with commercial operation expected at the end of 2028.

Questions and answers

What is the Hatzor solar-storage project?
It is a joint project by Timnat Energy and Colmobil Energy to build solar generation and energy storage at Kibbutz Hatzor’s reservoirs. The design uses existing water infrastructure with solar systems on the reservoir sides and floating solar panels on the water.
How much electricity will the project generate?
The system is expected to generate about 15.7 million kilowatt-hours a year, which equals the annual electricity consumption of about 2,000 households. Over 24 years, it is expected to generate about 360 million kilowatt-hours.
When will the project start operating?
Construction is scheduled to begin at the end of 2027, and commercial operation is expected at the end of 2028. The storage system is intended to supply electricity in the evening and during peak demand hours.

Share this story

About the writer

Shai Nogai

Writes for TV10, Israel’s economic channel. This story was translated from the original Hebrew.