First Permit Issued for a Metro Station in Israel

The licensing authority approved the start of work at Ariel Sharon Park on the M3 line • A massive excavation 38 meters deep will begin, involving complex logistics and a two-year timetable

Metro station
Metro station | Photo: Shutterstock

A dramatic and unprecedented step in advancing the largest transportation and infrastructure project in the country's history. The National Licensing Authority at the Planning Administration has issued, for the first time, authorization for a work permit to build an underground metro station.

Metro infrastructure in Tel Aviv
Metro infrastructure in Tel Aviv | Photo: Amos Luzon

The approval, issued under National Infrastructure Plan 103, marks the official transition from the planning and infrastructure relocation stage to the engineering work stage in the field. The first station where work will begin is the Ariel Sharon Park station, located in section A.1 of the M3 line.

Scope of Work and the Engineering Challenge

The underground structure of the new station will require the removal and excavation of about 300,000 cubic meters of soil.

Metro
Metro | Photo: Shutterstock

The work includes the construction of retaining walls at an exceptional depth of about 38 meters, reinforced with nine rows of ground anchors. This process is intended to prepare the infrastructure required for construction of the station and the passage of the underground railway tracks, with the planned duration of this work standing at about 25 months.

Logistical Preparations and Environmental Requirements

A dedicated staging area will be established at the site, including offices, logistics areas, a bentonite screening facility, a soil-drying area, a water treatment facility, and temporary electricity and lighting systems. Access to the site will be via a dedicated road prepared in advance, until the completion of a planned bridge in the area.

Ariel Sharon Park
Ariel Sharon Park | Photo: Nati Shohat/Flash90

Due to the proximity to Shapirim Stream and open areas, a stringent environmental appendix was drawn up in coordination with the Environmental Protection Ministry. It includes special guidelines for dust monitoring, restrictions on nighttime lighting, landscape restoration upon completion of the work, and compliance with noise standards in relation to the nearby communities of Azor and Ganot.

The Metropolitan Area's Connecting Ring

The M3 line, being advanced by NTA, is planned as a strategic ring line in the Tel Aviv metropolitan area. The line is expected to connect major residential, employment, commercial and medical centers, and will pass through, among other places, Bat Yam, Holon, Ariel Sharon Park, the Ono Valley, Sheba Medical Center at Tel Hashomer, Petah Tikva, Ramat HaHayal, Glilot and Herzliya.

Tel Aviv
Tel Aviv | Photo: Erik Marmor, Flash90

In addition, the plan includes a direct branch to Ben Gurion Airport and an operations complex, or depot, in Or Yehuda.

Extensive Coordination Among Authorities

The authorization was issued following complex coordination with dozens of entities, including the Israel Electric Corporation, Mekorot, Igudan, telecommunications companies, the Israel Antiquities Authority, the Yarkon Drainage Authority and the Ariel Sharon Park management.

Israel Electric Corporation
Israel Electric Corporation | Photo: Shutterstock

The Planning Administration and the National Infrastructure Committee say the completion of the licensing process constitutes a critical milestone and a professional platform that will enable the approval of the next stations in the national metro network to be accelerated.

Key takeaways

  • The National Licensing Authority issued the first work permit for an underground metro station in Israel under National Infrastructure Plan 103.
  • The first station to begin work is Ariel Sharon Park station in section A.1 of the M3 line.
  • The underground station will require excavation of about 300,000 cubic meters of soil and retaining walls about 38 meters deep reinforced with nine rows of ground anchors.
  • The planned duration of the work is about 25 months, with a dedicated staging area and special environmental conditions due to the site’s proximity to Shapirim Stream and open areas.
  • The M3 line is planned as a strategic ring line in the Tel Aviv metropolitan area and includes a direct branch to Ben Gurion Airport.

Questions and answers

What was approved for the first time in Israel’s metro project?
The National Licensing Authority at the Planning Administration issued the first authorization for a work permit to build an underground metro station. The approval marks the shift from planning and infrastructure relocation to field engineering work.
Where will the first metro station work begin?
Work will begin at the Ariel Sharon Park station, located in section A.1 of the M3 line. This is the first station to enter the engineering stage.
What are the main engineering challenges of the station work?
The project involves removing and excavating about 300,000 cubic meters of soil and building retaining walls to a depth of about 38 meters. The work is planned to take about 25 months.