Technology giant Google has signed an agreement to purchase 396 megawatts of geothermal electricity from Fervo Energy. The electricity is intended for a planned data center in the US state of Utah. According to the seller, this is the largest agreement ever signed for the purchase of electricity generated using enhanced geothermal systems.
Electricity supply is expected to begin in 2028 from the Cape Station project in southwestern Utah. Under the agreement, Google was given the option to increase its electricity purchases to 1 gigawatt by mid-2030. Following the announcement of the deal, Fervo Energy shares surged more than 25% in trading today (Tuesday).

Why Does Google Need Geothermal Energy?
The deal was signed amid the surge in electricity demand generated by the artificial intelligence revolution. Artificial intelligence models require enormous amounts of computing power, and data centers need a continuous electricity supply around the clock. Clean energy sources such as wind and solar depend on the weather and do not generate electricity continuously.
In addition, connecting new data centers to the power grid can take years because of strain on transmission and distribution infrastructure. Geothermal plants, by contrast, can provide electricity continuously and are a low-emission source. Fervo is developing enhanced geothermal systems that extract heat from hot rocks deep underground through drilling and water injection.

This technology makes it possible to generate electricity even in areas without a natural geothermal reservoir, significantly increasing the number of locations suitable for building power plants. The partnership between Google and Fervo began in 2021, when the two companies signed an agreement to jointly develop a next-generation geothermal project.
The Numbers Behind the Massive Project
The Cape Station project is expected to reach a potential capacity of 4.3 gigawatts and is described as the world's largest enhanced geothermal system. Before the agreement with Google, about 500 megawatts were under construction at the project. The new deal significantly increases the amount of electricity committed to customers and may make it easier for the company to secure financing for additional projects.
Fervo, which went public in May 2026, is in the early stages of growth. In its first quarterly report as a public company, it reported a net loss of $55.9 million and capital expenditures of $226.5 million. The company expects capital expenditures of up to $900 million in the second half of 2026, and its liabilities are expected to increase.
Before the deal with Google, Fervo held binding contracts to supply 658 megawatts, giving it a revenue backlog of about $7.2 billion. The new agreement is expected to significantly increase the backlog and make Google a major customer. Among the company's prominent investors is energy company Devon Energy, which holds about 13% of its shares.